FEASIBILITY, TESTING AND PRE- STUDY
REALIZATION
REALIZED AND FINISHED

FEASIBILITY, TESTING AND PRE- STUDY

Vorstudie

HALL D3/D4, photovoltaic system

Status:  Feasibility, testing and preliminary study

Project start: 2021

End of project: Open

Description :   A PV system with a nominal output of 1216 kWp generated by 3200 modules on an area of 5'870 sqm is to be installed on the roof areas of Halls D3 and D4 . The owner is Ferrowohlen AG.

HALL A, conversion

Status:  Feasibility, testing and preliminary study

Project start: Open

End of project: Open

Description :   The currently unused area of approx. 3'800 sqm is being redesigned as a padel tennis area in a preliminary project study.

HALL F, expansion of cold storage north

Status:  Feasibility, testing and preliminary study

Project start: January 2020

End of project: End of 2024

Description :   The FFF company would like to increase their storage space. The existing free space from the FFF car park is ideal for expanding your existing warehouse in the direction of Anglikerstrasse. Negotiations between FFF and Ferrowohlen are currently underway.

Infrastructure expansion

Status:  Feasibility, testing and preliminary study

Project start: 2023

Project end: 2025

Description :  The community of Wohlen intends to rehabilitate the works lines in the Industriestrasse section FFF to the Villmergerstrasse junction. From the Mühlerstrasse level crossing to the Anlikerstrasse junction, a pavement will be built on the Ferrowohlen lot. (Area approx. 1'000 sqm)

Realisierung

REALIZATION

HALL A, maintenance work

Status: Realization

Project start: 2018

Project end: 2022

Description :  The roof surfaces of the first projects from 2008 show various age-related leaks. The damaged spots and areas are repaired on an ongoing basis.

HALL A, maintenance work

Status:  Realization

Project start: 2019

Project end: 2022

Description :  After the completion of construction in 2017, the leaking channel was reported as a defect within the warranty period. In the course of remedying the defects, various measures were carried out under the direction of an external site manager via the contractor. Due to a constructive defect, the rectification of the defect will be completed in spring 2022 .

INFRASTRUCTURE EXPANSION, new sprinkler and retention basin east

Status:  Realization

Project start: January 2020

End of project: May 2022

Description :   The new location of the sprinkler basin is the existing, ground-level and open retention basin East. The new sprinkler and retention basin can be driven on by trucks or built over with a building. In addition, new and larger diesel pumps that meet FM Global requirements will be installed. The ring main of the sprinkler pressure line from the FM Global infrastructure project is therefore suitable. The previous sprinkler basin between halls A and B will be dismantled.

INFRASTRUCTURE EXPANSION,
Sprinkler basin East

Status: Realization

Project start: January 2020

End of project: May 2022

Description :  Development of the newly planned sprinkler and rainwater retention basin with:

 - sprinkler line

 - district heating

 - sewers

 - Fresh water

 - stream

 - conduits for data cables

REFURBISHMENT NEUTRALIZATION PLANT

Status:  Realization

Project start: January 2020

End of project: Summer 2022

Description :  In order to increase the operational reliability of the neutralization system and to reduce the operating costs, the aim is to automate the hydrochloric acid metering and the neutralization. The neutralization system should be set up in such a way that the addition is automatically adjusted to the requirement. Normally, only waste water that meets the requirements of the Water Protection Ordinance should be able to be discharged.

HALL A, expansion

Status:  Realization

Project start: 2020

Project end: 2023

Description :   Extension of the logistics areas with docking ramps. New construction of a social wing with cloakrooms, lounges and offices. Connecting passage between Halls A and B for goods and employees. 

HALL B, Middle, Digitec tenant fit-out

Status:  Realization

Project start: January 2020

End of project: Summer 2022

Description :  Digitec would like to increase its storage capacity on the Ferro Areal. The middle sector of Hall B is ideal for this.  The following changes would have to be made for the storage room:

 - Demolition of existing electrical room, sector north center

 - Addition of docking ramps

 - add fire protection concept

 - Reinforce EG floor for net loads of up to 1.75t/sqm

FLOOD PROTECTION

Status:  Realization

Project start: Autumn 2021

End of project: Summer 2022

Description :  Very heavy rain can cause too much surface water in the Bünztalstrasse area or on the parallel cycle path. So that this brief surface water can lead to flooding in Hall A, an approx. 40 cm high flood dam is being built.

Fertig

FEASIBILITY, TESTING AND PRE- STUDY

INFRASTRUCTURE EXPANSION,
New car park

Status:  Realized and finished

Project start: September 2019

Project end: April 2022

Description :   The goal with the construction of a new car park is that the employees of the tenants of the Ferro area park in the car park. This means that the existing parking areas in the area can be used for new buildings. The east parking garage has capacity for 951 parking spaces. 

NEW CONSTRUCTION HALL D3/D4

Status:  Realized and finished

Project start: Summer 2018

Project end: March 2021

Description :  New construction of a bonded warehouse and underground car park in the 1st basement. Construction: steel, concrete

Facade: sheet metal panels

Length: 125 m, width: 100 m, height 23 m

Floor area: 11'337 sqm

Usable area: approx. 21'000  sqm

Parking spaces: 121

HALL A, partial renovation of floor covering

Status: Realised and completed

Project start: Middle of 2021

Project end: February 2022

Description: Due to different subsidence in the subsoil, a ground elevation over an area of 80 sqm in the hard concrete floor slab had to be remediated during ongoing operation.

HALL A, dock shelters on loading ramps

Status:  Realized and finished

Project start: 2021

Project end: 2021

Description :  As a supplement, dock seals were attached to the loading ramps as winter heat protection. At the same time, the damaged door jambs were repaired.