FEASIBILITY, TESTING AND PRE- STUDY
HALL D3/D4, photovoltaic system
Status: Feasibility, testing and preliminary study
Project start: 2021
End of project: Open
Description : A PV system with a nominal output of 1216 kWp generated by 3200 modules on an area of 5'870 sqm is to be installed on the roof areas of Halls D3 and D4 . The owner is Ferrowohlen AG.
HALL A, conversion
Status: Feasibility, testing and preliminary study
Project start: Open
End of project: Open
Description : The currently unused area of approx. 3'800 sqm is being redesigned as a padel tennis area in a preliminary project study.
HALL F, expansion of cold storage north
Status: Feasibility, testing and preliminary study
Project start: January 2020
End of project: End of 2024
Description : The FFF company would like to increase their storage space. The existing free space from the FFF car park is ideal for expanding your existing warehouse in the direction of Anglikerstrasse. Negotiations between FFF and Ferrowohlen are currently underway.
Infrastructure expansion
Status: Feasibility, testing and preliminary study
Project start: 2023
Project end: 2025
Description : The community of Wohlen intends to rehabilitate the works lines in the Industriestrasse section FFF to the Villmergerstrasse junction. From the Mühlerstrasse level crossing to the Anlikerstrasse junction, a pavement will be built on the Ferrowohlen lot. (Area approx. 1'000 sqm)
REALIZATION
HALL A, maintenance work
Status: Realization
Project start: 2018
Project end: 2022
Description : The roof surfaces of the first projects from 2008 show various age-related leaks. The damaged spots and areas are repaired on an ongoing basis.
HALL A, maintenance work
Status: Realization
Project start: 2019
Project end: 2022
Description : After the completion of construction in 2017, the leaking channel was reported as a defect within the warranty period. In the course of remedying the defects, various measures were carried out under the direction of an external site manager via the contractor. Due to a constructive defect, the rectification of the defect will be completed in spring 2022 .
INFRASTRUCTURE EXPANSION, new sprinkler and retention basin east
Status: Realization
Project start: January 2020
End of project: May 2022
Description : The new location of the sprinkler basin is the existing, ground-level and open retention basin East. The new sprinkler and retention basin can be driven on by trucks or built over with a building. In addition, new and larger diesel pumps that meet FM Global requirements will be installed. The ring main of the sprinkler pressure line from the FM Global infrastructure project is therefore suitable. The previous sprinkler basin between halls A and B will be dismantled.
INFRASTRUCTURE EXPANSION,
Sprinkler basin East
Status: Realization
Project start: January 2020
End of project: May 2022
Description : Development of the newly planned sprinkler and rainwater retention basin with:
- sprinkler line
- district heating
- sewers
- Fresh water
- stream
- conduits for data cables
REFURBISHMENT NEUTRALIZATION PLANT
Status: Realization
Project start: January 2020
End of project: Summer 2022
Description : In order to increase the operational reliability of the neutralization system and to reduce the operating costs, the aim is to automate the hydrochloric acid metering and the neutralization. The neutralization system should be set up in such a way that the addition is automatically adjusted to the requirement. Normally, only waste water that meets the requirements of the Water Protection Ordinance should be able to be discharged.
HALL A, expansion
Status: Realization
Project start: 2020
Project end: 2023
Description : Extension of the logistics areas with docking ramps. New construction of a social wing with cloakrooms, lounges and offices. Connecting passage between Halls A and B for goods and employees.
HALL B, Middle, Digitec tenant fit-out
Status: Realization
Project start: January 2020
End of project: Summer 2022
Description : Digitec would like to increase its storage capacity on the Ferro Areal. The middle sector of Hall B is ideal for this. The following changes would have to be made for the storage room:
- Demolition of existing electrical room, sector north center
- Addition of docking ramps
- add fire protection concept
- Reinforce EG floor for net loads of up to 1.75t/sqm
FLOOD PROTECTION
Status: Realization
Project start: Autumn 2021
End of project: Summer 2022
Description : Very heavy rain can cause too much surface water in the Bünztalstrasse area or on the parallel cycle path. So that this brief surface water can lead to flooding in Hall A, an approx. 40 cm high flood dam is being built.
FEASIBILITY, TESTING AND PRE- STUDY
INFRASTRUCTURE EXPANSION,
New car park
Status: Realized and finished
Project start: September 2019
Project end: April 2022
Description : The goal with the construction of a new car park is that the employees of the tenants of the Ferro area park in the car park. This means that the existing parking areas in the area can be used for new buildings. The east parking garage has capacity for 951 parking spaces.
NEW CONSTRUCTION HALL D3/D4
Status: Realized and finished
Project start: Summer 2018
Project end: March 2021
Description : New construction of a bonded warehouse and underground car park in the 1st basement. Construction: steel, concrete
Facade: sheet metal panels
Length: 125 m, width: 100 m, height 23 m
Floor area: 11'337 sqm
Usable area: approx. 21'000 sqm
Parking spaces: 121
HALL A, partial renovation of floor covering
Status: Realised and completed
Project start: Middle of 2021
Project end: February 2022
Description: Due to different subsidence in the subsoil, a ground elevation over an area of 80 sqm in the hard concrete floor slab had to be remediated during ongoing operation.
HALL A, dock shelters on loading ramps
Status: Realized and finished
Project start: 2021
Project end: 2021
Description : As a supplement, dock seals were attached to the loading ramps as winter heat protection. At the same time, the damaged door jambs were repaired.