PROJECTS

Keep up to date with our ongoing projects. 

FEASIBILITY, TESTING AND PRE- STUDY
REALIZATION
REALIZED AND FINISHED
Machbarkeit
FEASIBILITY, TESTING AND PRELIMINARY STUDY

HALL D3/D4, photovoltaic system

Feasibility, testing and preliminary study

2021

Open

A PV system with a nominal output of 1216 kWp generated by 3200 modules on an area of 5'870 sqm is to be installed on the roofs of halls D3 and D4. The owner is Ferrowohlen AG.

HALL A, conversion

Feasibility, testing and preliminary study

Open

Open

The currently unused area of approx. 3'800 sqm is being redesigned as a padel tennis area in a preliminary project study.

Example expansion

Existing hall

HALL F, extension cold store north

Feasibility, testing and preliminary study

January 2020

End 2024

The company FFF would like to enlarge its storage space. For this purpose, the existing free space from FFF's car park lends itself to expanding their existing warehouse in the direction of Anglikerstreet. Negotiations are currently underway between FFF and Ferrowohlen.

INFRASTRUCTURE EXPANSION

Feasibility, testing and preliminary study

2023

2025

The municipality of Wohlen intends to rehabilitate the service pipes in the Industriestreet section from FFF to the Villmergerstreet junction. From the Mühlerstreet level crossing to the Anlikerstreet junction, a pavement will be built on the Ferrowohlen parcel. (Area approx. 1'000 sqm)

View towards the north

View towards the north

Realisierung
REALISATION

HALL A, maintenance work

Realisation

2018

2022

The roof surfaces of the first projects from 2008 onwards have various age-related leaks. The damaged spots and areas are being repaired on an ongoing basis.

Roof area Hall A

Roof area Hall A

Roof surfaces Hall A

Roof surfaces Hall A

HALL A, maintenance work

Realisation

2019

2022

After the completion of construction in 2017, the leaking gutter was reported as a defect within the warranty period. In the course of rectifying the defect, various measures were carried out under the supervision of an external construction manager via the contractor. Due to a constructional defect, the rectification of the defect will be completed in spring 2022.

Plan-Roofreperatur_CPE.jpg

INFRASTRUCTURE EXPANSION, East sprinkler basin

Realisation

January 2020

May 2022

Development of the newly planned sprinkler and rainwater retention basin with:

 - sprinkler pipe

 - district heating

 - sewerage

 - fresh water

 - electricity

 - empty pipes for data cables

July 2021

March 2022

INFRASTRUCTURE EXPANSION, new construction of sprinkler and retention basin East

Realisation

January 2020

May 2022

The new location of the sprinkler basin is the existing, ground-level and open retention basin East. The new sprinkler and retention basin can be accessed by trucks or covered with a building. In addition, new and larger diesel pumps that meet FM Global requirements will be installed. This means that the ring main of the sprinkler pressure line is suitable for the FM Global infrastructure project. The existing sprinkler basin between halls A and B will be dismantled.

​

May 2020

June 2021

December 2021

REFURBISHMENT NEUTRALISATION PLANT

Realisation

January 2020

Summer 2022

In order to increase the operational safety of the neutralisation plant and reduce the operating costs, the aim is to automate the dosing of hydrochloric acid and neutralisation. The neutralisation plant is to be set up in such a way that the addition is automatically adjusted to the demand. Normally, it should only be possible to discharge wastewater that meets the requirements of the Water Protection Ordinance.

​

December 2019

December 2021

HALL B, centre, Digitec tenant fit-out

Realisation

January 2020

Summer 2022

Digitec would like to increase its storage capacity on the Ferro site. The middle sector of Hall B is suitable for this purpose.  The following changes would have to be made to the storage space:

 - deconstruction of existing electrical room, north-centre sector.

 - addition of docking ramps

 - supplement fire protection concept

 - reinforce the ground floor for net loads of up to 1.75t/sqm.

December 2019

December 2021

December 2021

December 2021

December 2021

December 2021

HALL A, expansion

DJI_0151.JPG

Realisation

2020

2023

Expansion of the logistics areas with docking ramps. New construction of a social wing with cloakrooms, lounges and offices. Connecting passerelle between halls A and B for goods and employees. 

Expansion A.jpg

View north

FLOOD PROTECTION

Realisation

Autumn 2021

Summer 2022

Very heavy rainfall can lead to a lot of surface water in the area of the Bünztalstreet and the parallel cycle path. To ensure that this short-term surface water can lead to flooding in Hall A, an approx. 40 cm high flood embankment is being built.

Flood.jpg
REALISED AND COMPLETED
Realisiert

Realisation

September 2019

April 2022

The aim of building a new multi-storey car park is for the employees of the tenants of the Ferro site to park in the car park. This means that the existing parking spaces in the area can be used for new buildings. The East multi-storey car park has capacity for 951 parking spaces. 

INFRASTRUCTURE EXPANSION, new construction of multi-storey car park 

NEW BUILDING HALL D3/D4

Realised and completed

Summer 2018

March 2021

New construction of a bonded warehouse and underground car park on the 1st floor.

Construction: steel, concrete

Facade: sheet metal panels

Length: 125 m, width: 100 m, height 23 m

Floor space: 11'337 sqm

Usable floor space: approx. 21'000 sqm

Parking spaces: 121

West flood embankment

D3-D4.jpg

HALL A, partial renovation of flooring

Realised and completed

Middle 2021

February 2022

Due to different settlements in the subsoil, a ground elevation over an area of 80 sqm in the hard concrete floor slab had to be remediated during ongoing operations.

Old 201

New 2021

HALLE A, Door seals on loading ramps

Realised and completed

2021

2021

In addition, door seals were installed at the loading ramps as winter thermal protection. At the same time, the damaged door reveals were renovated.

Milling off concrete

​Finished renovated concrete slab